Tehran Refinery Product Quality Upgrading Project (PMC/SSC Services) |
||
|
In Nov. 2007 EIED signed the Contract for Project Management Services/Site Supervision Services (PMC/SSC) of Tehran Refinery Product Quality Upgrading Project with the Client (National Iranian Oil Engineering & Construction-NIOEC). The EPC Contractor is EHSAN joint venture consisting of ODCC, IGC, and Design & Inspection Engineering Co. The Project Scope consisting of Licensed and Non-licensed units is as follows: 1- Gas oil Desulfurization Unit, Axens (IFP) License, (53,500 bpd) 2- Kerosene Desulfurization Unit, Axens (IFP) License, (28,000 bpd) 3- Hydrogen Plant, (42 million CFD) 4- Power Generation Plant and related facilities (35 MW) 5- Downstream Units Revamping/Adding as required (LPG Recovery, Sour Water Unit, Amine Treatment Unit, Sulfur Recovery Unit, Storage Tanks, Flare) The duration and type of EIED services are as follows: A) General PMC Services (44 months) B) Engineering and Procurement Supervision Services (32 months) C) Site Supervision Services (20 months)
|
||
|