Sirri Island Gas Gathering and NGL Recovery Complex (E)
The Sirri NGL Complex is designed to produce 6,900 Barrel/day Propane, 3750 Barrel/day Butane, 3,180 Barrel/day Condensate and 50 MMSCFD Feed gas for Kish & Qeshm Islands, by using 140 MMSCFD Sour Gas Feed.

The NGL Complex is located in an 18 Hectare Area at Sirri Island in the Persian Gulf. The EPC Contractor’s Scope of Work includes Basic and Detailed Engineering, Procurement, and Construction.

The NGL Complex consists of the following units:

  1.  

  2. v   Feed gas compression                          

  3. v   Acid gas removal unit

  4. v   Acid gas incinerator

  5. v   Dehydration unit

  6. v   NGL recovery unit

  7. v   NGL fractionation to Propane, Butane and Condensate

  8. v   NGL refrigeration

  9. v   Cryogenic Propane and Butane storage

  10. v   Propane and Butane boil off gas recovery

  11. v   Propane and Butane export by fully refrigerated gas carrier

  12. v   Condensate stabilization, storage and export

  13. v   Utility systems

  14. v    Off site

  15.  

  16. The Owner is Iranian Offshore Oil Company (IOOC) and the EPC Contractor is OIEC .The EPC Contract duration between IOOC and OIEC is 40 months from its Effective Date.

  17. OIEC has awarded the following Engineering Services to EIED under an Engineering Contract.

  18.  

  19.  Endorsement of the Basic Design Package

  20.  Detail Engineering Design for the Complex

  21.  Procurement Engineering Services

  22.  Field Engineering Services during erection, installation and construction of the Complex

  23.  Field Engineering during Pre-commissioning and Commissioning of the Complex

  24.  Preparation of tender documents for construction work packages

  25.  

  26. The Engineering Contract duration between EIED and OIEC is 28 months from its Effective Date.

 